Construction

| Model Testing | Command and Control | Profile | Propulsion | Accommodations |

The USCGC MACKINAW (WLBB-30) was built by Marinette Marine Corporation, a subsidiary of Manitowoc Marine Group.  The cutter was assembled indoors in the Vessel Erection Building.  This allowed the vessel to be assembled and outfitted in controlled conditions, then moved outside to the launch ways.

The cutter was constructed in a planned system of modules or blocks that are fabricated and pre-outfitted prior to being moved to the erection building. This method of construction is extremely efficient as it provides easy access to equipment, components, and spaces. The modules are essentially complete prior to final assembly.

USCGC MACKINAW (WLBB-30) Construction Timeline

Fabrication Began April 14, 2004
Keel Laid February 9, 2004
Launched April 2, 2005
Commissioned June 10, 2006

Early construction Early construction Early constructionEarly construction Early construction

Download Plug-Ins
Download Plug-Ins: Some of the links on this page require a plug-in to view them. Links to the plug-ins are available below.
Click Here to Download Adobe Acrobat Reader Adobe Acrobat Reader (PDF)
Last Modified 8/18/2014